40 First Nations communities still under long-term drinking water advisories — where the projects stand

By Water Canada Staff

As of May 2026, data from Indigenous Services Canada (ISC) indicates that 40 long-term drinking water advisories (LTDWAs) remain in effect across 37 First Nations communities. While the headline number remains a point of political debate, the engineering reality on the ground is one of high-intensity construction. Of the remaining 40 advisories, over 80 per cent have active infrastructure projects currently in the design or construction phases.

Under Construction: 5 Communities to Watch in 2026

The path to lifting an advisory is rarely linear, often involving multi-year construction cycles. Here is a status update on five key projects currently in the construction phase:

1. Neskantaga First Nation, Ontario

Advisory Since: February 1995

Project Scope: Comprehensive upgrade to the existing water treatment plant and distribution system to address long-standing structural integrity issues.

Current Status: Final mechanical commissioning. Following a series of setbacks in 2024, the project is now entering the 24-hour testing phase.

Estimated Completion: Late Summer 2026

2. North Spirit Lake First Nation, Ontario

Advisory Since: May 2001

Project Scope: Construction of a brand-new water treatment plant and intake system to replace the decommissioned facility.

Current Status: Structural build is 90% complete. Electrical and controls installation is currently underway by contractors.

Estimated Completion: December 2026

3. Oneida Nation of the Thames, Ontario

Advisory Since: September 2019

Project Scope: Major pipeline connection project to link the community to the regional Lake Huron water supply system.

Current Status: Trenching and pipe-laying are active. Over 15km of the connection is now in the ground.

Estimated Completion: Autumn 2026

4. Tataskweyak Cree Nation, Manitoba

Advisory Since: June 2017

Project Scope: Expansion of treatment capacity and implementation of advanced filtration to deal with high turbidity and organic loads.

Current Status: Construction of the filtration annex is complete; membrane installation began in April 2026.

Estimated Completion: Spring 2027

5. Shamattawa First Nation, Manitoba

Advisory Since: December 2018

Project Scope: System-wide emergency repairs and the construction of a new reservoir to ensure consistent pressure and fire safety.

Current Status: Foundation for the reservoir has been poured. Logistical challenges due to winter road conditions have pushed the final phase to this summer.

Estimated Completion: November 2026

Tracking the 2026 Pipeline

While these five projects represent the “heavy lifting” currently in the construction phase, ISC tracking indicates that an additional 12 communities are in the final feasibility or design stages. For these nations, the focus remains on securing procurement and identifying

qualified contractors—a task made increasingly difficult by the nationwide shortage of specialized civil and water engineers.

*Project data sourced from the Indigenous Services Canada (ISC) “Ending Long-Term Drinking Water Advisories” dashboard and community-led infrastructure updates as of May 2026.*

Sidebar: Essential Water Watchlist

Stay informed on Canada’s water landscape with these high-authority tracking tools and policy resources:

Leave a Reply

Your email address will not be published. Required fields are marked *

water canada

Get weekly updates in your inbox on the projects, policies, and people you need to know about.