Mapleton Wastewater Capacity Upgrades

Province: Ontario

City/Region: Drayton

Image Credit: Graham Construction

46

Project Rank

Project Start: 2024

Project End: 2027 (Phase 1)

Project Amount: $41 Million

Industry Sector: Wastewater

Funding Source: N/A

LEED Status: N/A

YearRank

About The Project

In early 2024, the Township partnered with Graham Capital, an expert in “project financing and alternative delivery models”. Graham identified an opportunity for Mapleton to establish an MSC to a long-term sustainable financing structure that preserves municipal borrowing capacity while advancing essential infrastructure projects. 

Northern Maple Utilities Inc. was officially established as an MSC in the spring of 2025. This new entity will be responsible for the ongoing operations, maintenance, asset renewal, and delivery of water and wastewater services to the Township of Mapleton.

The water and wastewater upgrades needed include:

  • Upgrades to the Mapleton Wastewater Pollution Control Plant (WPCP);
  • Upgrades to Drayton and Moorefield Sewage Pumping Stations;
  • Improvements to water and wastewater distribution systems; and
  • Construction of new water and wastewater pumping stations.

Project Owner: Northern Maple Utilities Inc.

Project/Construction Manager: Graham Capital

Engineer: CIMA+

Contractor: Graham Construction and Engineering Inc.

Other Key Players: Ontario Clean Water Agency (Operations and Maintenance); BTY (Lender Technical Advisor); TD Asset Management (Lender)

Key Players

Key Players’ recognize the organizations whose work, knowledge, and expertise go into constructing and delivering the significant projects that make our annual list.

Platinum (12+ Projects)

Gold (9-11 Projects)

Silver (6-8 Projects)