Springbank Off-Stream Reservoir

Province: Alberta

City/Region: Calgary

11

Current Rank

Project End: 2025

Project Amount: $744 Million

Industry Sector: Stormwater

Funding Source: Public

LEED Status: N/A

YearRank
20249

About The Project

WHEN OPERATIONAL, the Springbank Off-Stream Reservoir Project (SR1) will work in tandem with the Glenmore Reservoir and other flood mitigation infrastructure in and around Calgary.

The SR1 Project includes: a diversion structure on the Elbow River; a 4.7-kilometre diversion channel; a 29-metre earthen dam stretching approximately 3.8 kilometres; and a series of hydraulic structures and two overpass bridges above the diversion channel, totalling 70,000 cubic metres of reinforced concrete. In total, earth work volume for this project is estimated at around five million cubic metres.

Project Owner: Alberta Transportation and Economic Corridors

Engineer: Stantec; Golder (WSP) (environmental); Wood (WSP) (consulting)

Contractor: VINCI Infrastructure Canada (general contractor)

Environmental Services: Stantec

Other Key Players: Graham (bridges and concrete structures); EY (risk advisor)

Key Players

Key Players’ recognize the organizations whose work, knowledge, and expertise go into constructing and delivering the significant projects that make our annual list.

Platinum (15+ Projects)

Sorry, there are no results for this section

Gold (9-14 Projects)