Don River and Central Waterfront & Connected Projects
Province: Ontario
City/Region: Toronto
4
Current Rank
Image Credit: Actual Media
Project End: 2038
Project Amount: $3 Billion
Industry Sector: Stormwater
Funding Source: Public
LEED Status: N/A
Year | Rank |
---|---|
2024 | 4 |
About The Project
TORONTO IS embarking on the largest and most significant stormwater management program in the city’s history. This program will greatly improve the water quality in the Lower Don River, Taylor Massey Creek and along Toronto’s Inner Harbour by keeping combined sewer overflows out of our waterways by upgrading technology and increasing the system’s capacity to capture, transport and treat them.
The project consist of an integrated system of tunnels, storage shafts, connections, an integrated pumping station, a high-rate treatment facility, a real-time control system and wastewater treatment plant upgrades. The program is made up of several individual projects that will work together, including the Don River and Central Waterfront Wet Weather Flow System, the Ashbridges Bay Treatment Plant (ABTP) Integrated Pumping Station, ABTP Ultra-Violet (UV) Disinfection Facility, ABTP Landform and high-rate treatment facility, and the ABTP Outfall.
Project Owner: City of Toronto
Program Manager: Don River and Central Waterfront Wet Weather Flow System (DR&CW WWF System): • Coxwell bypass (stage 1): Black & Veatch Canada in association with R.V. Anderson Associates Limited (consultants); North Tunnel Constructors (contractor) • Inner Harbour West Tunnel: Hatch/AECOM (consultant) • Mid-Toronto-Interceptor (MTI) Real-Time Control: Tetra Tech (consultant) • Integrated Pumping Station (IPS): Black & Veatch Canada in association with R.V. Anderson Associates Ltd. (consultants); Strabag Canada (contractor-contract 2) • Ashbridges Bay Landform Project: Toronto and Region Conservation Authority (TRCA) with Shoreplan Engineering (designer); TRCA (constructor of landform) • UV (Ultraviolet) Disinfection Facility: AECOM (consultants); Graham (contractor) • Outfall: Hatch, Jacobs and Baird (consultants); (SAJV) Southland Astaldi Joint Venture (contractor)
Other Key Players: Wood (WSP) (environmental engineer/geotechnical studies); Golder (WSP) (geotechnical services); Arcadis-IBI Group (risk assessment); LEA Consulting (engineer-planning); R.V. Anderson Associates Ltd.; E.S. Fox; Arup (engineer); KSB PUMPS INC (product supplier)

Key Players
Platinum (15+ Projects)
Sorry, there are no results for this section