Buffalo Pound WTP Renewal Project

Province: Saskatchewan

City/Region: Near Buffalo Pound Lake

18

Current Rank

Project End: 2026

Project Amount: $325.6 Million

Industry Sector: Drinking Water

Funding Source: Public

LEED Status: N/A

YearRank
202417

About The Project

THE RENEWAL project will upgrade the main treatment plant, treatment processes and treatment technologies, as well as modernizing the facility with necessary redundancy. It will rejuvenate the plant, enabling it to meet the region’s forecasted potable water demands for the years ahead.

Construction began in June on the project. Work to date includes construction on temporary roads and lay down areas, the start of new summer ponds, relocation of a natural gas line, initiation of chemical tank refurbishment, and the start of various underground services. The plant renewal project is expected to be completed and fully operational by the end of 2025.

Project Owner: Buffalo Pound Water Treatment Corporation (SK)

Project/Construction Manager: JV Graham Infrastructure Inc. – Aecon Water Infrastructure Inc.

Engineer: Stantec; Associated Engineering

Other Key Players: KSB PUMPS INC. (Product Supplier), Graham (Project Manager/Construction Manager, Contractor)