Current Rank
Project Start: 2024
Project End: 2030
Project Amount: $261 Million
Industry Sector: Wastewater
Funding Source: Public
LEED Status: N/A
Year | Rank |
---|---|
2024 | 18 |
About The Project
ACTUAL CONSTRUCTION began in 2024 and is scheduled to be completed in 2030. It includes
upgrading or replacing electrical substation infrastructure to service future needs and converting the high purity oxygen biological system to a conventional fine bubble aeration system.
The upgrades also include new flow facilities to address the peak flows at the plant and the construction of a fourth digester to increase solids handling capacity.
Project Owner: City of Barrie
P3 Team Members/Project Team: Maple-Bird Joint-Venture (Maple Reinders; Bird Construction); WSP Canada; Stantec